EDILIZIA
EXPANSION AND RENOVATION OF A BUILDING IN VIA RIPAMONTI N. 436 MILAN
-
European Institute of Oncology
-
Works amount: € 11.782.669,30
-
Works start: 30November 2009
-
Works end: 30 September 2011
-
Works status: Completed
STORAGE AREA AND HANDLING OF UREA IN MARSA BREGA (LIBYA)
-
LIFECO (Libyan Norwegian Fertilizer Company)
-
Works amount: € 25.770.000
-
Works start: 07 July 2015
-
Works end: In progress
-
Works status: In progress
AUCHAN – SHOPPING CENTRE IN BUSSOLENGO (VR-ITALY)
-
AUCHAN S.p.A.
-
Works amount: € 19.274.000
-
Works start: 8 October 2015
-
Works end: Completed
-
Works status: Completed
“AUCHAN” MALL – RESTYLING AND EXPANSION PROJECT
-
Galleria Commerciale Italiana S.p.A.
-
Works amount: € 4.210.607,47
-
Works start: 28 September 2017
-
Works end: 6 September 2018
-
Works status: Completed
SHOPPING CENTER PALLADIO – VICENZA
-
UNICOMM s.r.l. – Malo (VI)
-
Works amount: € 15.906.872,49
-
Works start: 18 November 1999
-
Works end: 21 July 2004
-
Works status: Completed
SHOPPING CENTRE “METAURO” – EXPANSION AND RESTYLING INTERVENTION IN FANO (ITALY)
-
Auchan S.p.A.
-
Works amount: € 12.120.574
-
Works start: 02 December 2016
-
Works end: 10 Otcober 2017
-
Works status: Completed
THERMAL CENTRE FORDONGIANUS – NUORO
-
Italian Region of Sardinia
-
Works amount: € 24.209.408,07
-
Works start: 5 June 1995
-
Works end: 2 July 2004
-
Works status: Completed
CITY OF CALDOGNO – VICENZA
-
Comune di Caldogno – Project Financing
-
Works amount: € 80.000.000,00
-
Works start: 18 July 2008
-
Works end: 12 January 2010
-
Works status: Completed
MULTIFUNCTIONAL COMPLEX “ETNAPOLIS” - CATANIA
-
Alis Imobiliare C.T.A. S.p.A. – Belpasso (CT)
-
Works amount: € 140.500.000,00
-
Works start: 13 May 2003
-
Works end: 13 July 2006
-
Works status: Completed
CONSTRUCTION OF THE RETAIL PARK MARKET DA VINCI
-
M.C.F. S.r.l.
-
Works amount: € 25.299.672,88
-
Works start: 12 July 2006
-
Works end: 18 October 2007
-
Works status: Completed
MILITARY HOSPITAL CONSTRUCTION AL KHOUDH (OMAN)
-
Ministry of Defense
-
Works amount: € 46.373.970,00
-
Works start: 06 October 2015
-
Works end: 3 March 2019
-
Works status: Completed
CONSTRUCTION OF A MALL CALLED “AREA SERENISSIMA” - VICENZA
-
Maltauro Immobiliare Srl
-
Works amount: € 77.500.000,00
-
Works start: April 1992
-
Works end: December 2004
-
Works status: Completed
BUILDING FOR INTEGRATED LABS FOR TECHNOLOGIES, CHEMICAL PROCESSES AND NUCLEAR ENGINEERING AND RADIATIONS - NEW DEPARTMENT OF ENERGY - CAMPUS BOVISA - MILAN
-
Politecnico di Milano
-
Works amount: € 14.041.650,97
-
Works start: 1 March 2010
-
Works end: 15 October 2012
-
Works status: Completed
MULTI-PURPOSE BUILDING A.P.I.
-
API Immobiliare S.r.l.
-
Works amount: € 18.750.821,74
-
Works start: 28 July 2006
-
Works end: 10 September 2009
-
Works status: Completed
LOGISTIC BUILDING ADJACENT TO THE INDUSTRIAL COMPLEX EASTGATE PARK
-
Pirelli SpA
-
Works amount: € 11.500.000,00
-
Works start: 27 July 2007
-
Works end: 13 October 2008
-
Works status: Completed