Industriale

Agip Oil Co. Ltd
  • Works amount: € 1.000.000
  • Works start: 1996
  • Works status: Completed
  • Works amount: € 14.675.000
  • Works start: 07 july 2015
  • Works end: In progress
  • Works status: In progress
Impianto di prefabbricazione di Azzawia – Libia
  • Works amount: € 30.000.000
  • Works start: 01 dicember 2008
  • Works end: In progress
  • Works status: Completed
Impianto frazionamento aria presso il cantiere Sapio produzione idrogeno ossigeno s.r.l.

AIR SEPARATION PLANT AT THE YARD SAPIO PRODUZIONE IDROGENO OSSIGENO S.R.L.

  • Works amount: € 11.879.913,46
  • Works start: 1 february 2009
  • Works end: 31 august 2010
  • Works status: Completed
Insediamento produttivo, artigianale e industriale dell'area   Ex Falck   concordia sud – Milano

PRODUCTIVE, ARTISAN AND INDUSTRIAL SETTLEMENT IN THE “EX FALCK” AREA CONCORDIA SUD - MILA

  • Works amount: € 17.455.732,76 (n. quota 51%)
  • Works start: 15 January 2001
  • Works end: 28 february 2003
  • Works status: Completed
Lavori civili
  • Works amount: € 1.072.913.160
  • Works start: 1 july 2012
  • Works end: 8 july 2017
  • Works status: Completed
Lavori civili del nuovo stabilimento per la lavorazione del latte con annessi uffici - Nuova Centrale del latte di Vicenza

CIVIL WORKS OF THE NEW PLANT FOR THE PRODUCTION OF MILK WITH ANNEX OFFICES

  • Works amount: € 16.070.000,00 (Capogruppo 91,97%)
  • Works start: 10 march 2005
  • Works end: 10 june 2008
  • Works status: Completed
Lavori nei siti industriali di Marghera e Ferrara

WORKS IN THE INDUSTRIAL SITES OF FERRARA AND MARGHERA

  • Works amount: €  157.000.000,00
  • Works start: 1990
  • Works end: In progress
  • Works status: In progress
Nuova fabbrica di inscatolamento del pesce
  • Works amount: € 6.500.000
  • Works start: 1999
  • Works status: Completed
Nuova stazione elettrica 380/150 Kv di Villafranca Tirrena (ME)

NEW ELECTRIC STATION 380/150 KV IN VILLAFRANCA TIRRENA (ME)

  • Works amount: €  22.406.111,00
  • Works start: 3 may 2010
  • Works end: In progress
  • Works status: Completed
Progetto Est del cantiere Eni-Saipem Ferrera Erbognone (PV)

EAST PROJECT OF THE YARD ENI-SAIPEM FERRERA ERBOGNONE (PV)

  • Works amount: € 11.805.045,88  (nostra quota 75%)
  • Works start: 01 november 2010
  • Works end: 20 august 2013
  • Works status: Completed
Realizzazione del polo logistico di Carpi (Mo)

Logistic building constructionin Carpi (Mo)

  • Works amount: € 8.106.762,00
  • Works start: 1 january 2018
  • Works end: September 2019
  • Works status: Completed
Realizzazione di nuovo insediamento logistico (edificio D) presso l'area denominata macroarea T2

New logistic building constructionn(building D) within the economical area named "Macroarea T2" in Piacenza

  • Works amount: € 28.897.422,44
  • Works start: 12 october 2017
  • Works end: 9 August 2018
  • Works status: Completed
Stabilimento Liatec

LIATEC FACILITY

  • Works amount: € 12.277.000,00
  • Works start: 09 June 2008
  • Works end: 07 May 2013
  • Works status: Completed

Copyright © 2018. All Rights Reserved Gruppo ICM SPA - 36100 - VICENZA Viale dell'Industria 42 Tel. 0444/336111 Fax 0444/961541 P.IVA - 02526350240 - Privacy e Policy
Powered by Tech&WebSolutions.it

Cookies make it easier for us to provide you with our services. With the usage of our services you permit us to use cookies.
Ok