AIRPORT OF PANTELLERIA
-
ENAC Ente Nazionale per l’Aviazione Civile
-
Works amount: € 21.430.372,80
-
Works start: 1 August 2009
-
Works end: 7 May 2013
-
Works status: Completed
REQUALIFICATION AND REGULATORY UPGRADE OF THE RUNWAY LOT 2 - 2ND PHASE OF THE VENICE AIRPORT
-
S.A.V.E. S.p.A.
-
Works amount: € 120.547.368,86
-
Works start: 1 September 2018
-
Works end: 30 June 2020
-
Works status: Completed
Civil, Infrastructural and Maintenance Works
-
LEONARDO S.p.A.
-
Works amount: Euro 182.533.291
-
Works start: 20/01/2022
-
Works status: In progress
REHABILITATION WORKS FOR HANGARS N. 1, 2 AND 3 OF AVIANO AIRPORT
-
Ministry of Defense - General Directorate of Works and State Property
-
Works amount: € 12.527.617,00
-
Works start: 1 February 2007
-
Works end: 1 March 2013
-
Works status: Completed
MULTIPLE AWARD CONSTRUCTION CONTRACT DJIBOUTI
-
US Navy (NAVFAC ATLANTIC)
-
Works amount: € 35.000.000
-
Works start: 26 October 2018
-
Works end: ongoing
-
Works status: In progress
DESIGN-BUILD / DESIGN-BID-BUILD MULTIPLE AWARD CONSTRUCTION CONTRACT NAPLES
-
US Navy (NAVFAC EUROPE SOUTHWEST ASIA)
-
Works amount: € 16.756.000
-
Works start: 26 September 2018
-
Works end: ongoing
-
Works status: In progress
MATOC VICENZA (Multiple Award Task Order Contract)
-
US Army
-
Works amount: € 8.640.000
-
Works start: 10 July 2018
-
Works end: ongoing
-
Works status: In progress
MODIFICATIONS FOR AL-UDEID EXISTING BUILDING TO ACCOMODATE RAFALE TEMPORARILY (Z-304-01)
-
Qatar Armed Forces
-
Works amount: € 11.809.200
-
Works start: 19 September 2019
-
Works end: 30/03/2020
-
Works status: Completed
P655 P-8A HANGAR AND FLEET SUPPORT FACILITY AND P407 TRITON HANGAR AND OPERATION FACILITY – SIGONELLA (CT) ITALIA
-
NAVFAC Atlantic Division
-
Works amount: € 45.200.000
-
Works start: 12 December 2016
-
Works end: ongoing
-
Works status: In progress
INTERNATIONAL AIRPORT PRAIA (CAPE VERDE)
-
Ministere des Infrastrucutre et Economie Maritime
-
Works amount: € 26.950.000
-
Works start: 21 april 2006
-
Works end: 31 May 2019
-
Works status: Completed
South Ramp, Zulu Arm/Dearm Pad, Expand North Ramp - Aviano Air Base
-
Naval Facilities Engineering Command Europe and Southwest Asia ROIC AVIANO
-
Works amount: € 8.667.056,00
-
Works start: 24 August 2004
-
Works end: 19 December 2005
-
Works status: Completed